Question:
ACTIVITY | ACTIVITY | ||||
---|---|---|---|---|---|
ACTIVITY | ACTIVITY PREDECESSOR | NORMAL (WEEKS) | CRASH (WEEKS) | NORMAL ($) | CRASH ($) |
1 | - | 20 | 8 | 1,000 | 1,480 |
2 | - | 24 | 20 | 1,200 | 1,400 |
3 | - | 14 | 7 | 700 | 1,190 |
4 | 1 | 10 | 6 | 500 | 820 |
5 | 3 | 11 | 5 | 550 | 730 |
A) Construct the project network.
B) Determine the maximum possible crash time for the network, and the crash the network the maximum amount possible.
C) Compute the normal project cost and the cost of the crashed project.
Networking
Networking refers to the transfer of data, facts and figures. For the organization, networking is used to analysis the time and cost incurred in the particular activity. The network analysis is sued to minimize the cost incurred and determine the maximum cost and duration of the activity.
Answer and Explanation:
Become a Study.com member to unlock this answer!Createyouraccount
A) Construct the project network.
B) Determine the maximum possible crash time for the network, and the crash the network the maximum amount...
See full answer below.