MRP Planning Process | SAP Blogs (2024)

Dear SAP Friends,

In this blog will try to Explore different Planning Process used for Full filling Business Needs.

We use special planning processes, for below reasons

  • if we do not want to plan on a plant level, but eitheron a multi-plant levelor only for a part of a plant
  • if we want to work withspecial procurement types.

Special planning processes include

  1. Subcontracting
  2. Direct production
  3. Direct procurement
  4. Storage location MRP
  5. Planning with MRP areas
  6. Multi-plant/site planning
  7. Requirements grouping for individual project planning

As the Content is vast will split in to 2 Parts in First part will cover

Subcontracting

Direct Production

Direct Procurement

Storage Location MRP

In subcontracting, the vendor is provided with materials (components), which he uses to produce the finished product.

Integration

  • From the point of view of materials planning, subcontracting is initiated by the special procurement keySubcontracting. The special procurement key is allocated to the finished product or the assembly in the material master (MRP 2view) In order to plan specific material requirements for each individual subcontractor, we can use MRP areas. We can thereby create an individual MRP area for every subcontractor.

If an assembly is produced bydifferent subcontractorsor produced in-house withdifferent BOMs, the system is to take this into account during the BOM explosion in the planning run.

Prerequisites

  • We have entered the special procurement keySubcontractingin the material master (MRP 2view) of the assembly.
  • We have created aproduction versionin the material master (MRP 4view) of the assembly, in which we have entered thealternative BOMrelevant to the subcontractor/vendor.
  • We have entered thisproduction versionin thepurchasing info recordfor the subcontractor.
  • We have entered thesubcontractorin thesource listor in thequota arrangementfor this assembly.If we do not use quota arrangements, we have to set theRecord relevant to MRPindicator in the MRP column of thesource list.
  • We have set theScheduling info record/agreementindicator in Customizing for MRP in the IMG activityDefine external procurement.

Integration

We can find the transactions for maintaininginfo recordsand thesource listin thePurchasingmenu, underMaster data.

Features

  • Material requirements planning adopts theproduction version from the subcontractor’s purchasing info recordand explodes the correspondingalternative BOMthat is defined in the production version. This also applies to planned orders and purchase requisitions.

Caution

The production version from the subcontractor purchasing record has a higher priority than the production version from the quota arrangement.

  • In Purchasing, when assigning the source of supply, the production version is copied from the subcontractor info record into the purchase requisition or purchase order and is used for selection in the BOM.
  • Production versions that we have entered in the quota arrangement are considered in MRP and Purchasing.

Use

If wedo not use direct production, no link exists between the planned orders/production orders within the BOM structure. This means that the production order is scheduled individually, and costs are dealt with individually for every assembly and component (except for make-to-order production – here we can jointly consider the costs for several production levels). Once production is finished, the goods receipt for these components is posted in the warehouse so that goods issue of the components can be carried out for the production order of the superior assembly.

In contrast, the aim of direct production is to jointly regardschedulingandcosting proceduresfor finished products, assemblies and components within a BOM structure.

The components that are produced directly relate to each other in a multi-levelcollective orderby entering the respective superior and leading planned order or production order. The collective order can be scheduled together and the costs incurred for the collective order can also be dealt with together

A further advantage of direct production is the simplified process: Components that are produced directly are not placed in stock and are consumed directly by the superior production order. No manual goods receipt/issue postings are necessary. These postings are increasingly executed automatically during the confirmation of an operation in a production order.

Caution

Direct productiondoes notconsider available plant stock.

Prerequisites

  • If we want to use direct productionfor a componentall the time, we have entered the special procurement key for direct production in the material master for the component (MRP 2view).
  • If we want to use direct procurementfor a BOMonly, we have entered the special procurement key for direct procurement in the corresponding BOM item in theMRP data This entry overwrites the entry in the material master.

Note

If we have activated direct production in the material master, we can switch off direct production for a BOM, if we deactivate direct production in theMRP dataarea of the corresponding BOM item underExplosion type. This entry overwrites the entry in the material master.

Features

Direct production is always triggered in the planning run.

  • A special indicator is set internally fordependent requirementsof the components that are produced directly. This passes on the relevant information for direct production to MRP. During the planning of these components, the system creates correspondingplanned orders for direct productionfor these dependent requirements. The system displays dependent requirements and planned orders for direct production in a separatedirect production segmentin the MRP list and the stock/requirements list.
  • When the planned order for the finished product is converted into a production order, all planned orders for subordinate components that are to be produced directly are automatically converted into production orders.
  • The system adapts planned orders for direct production to changes in date and quantity of the superior assembly, even if they are firmed, so that the consistency of the collective order is kept. Manual changes are reversed.

Whenfirmed purchase requisitions for direct production are changed, the system automatically sends the MRP controller amailwith the data for the change

Using thedirect procurementprocedure, we can order BOM components for a planned order directly instead of via the warehouse.

Note

Direct procurement is also possible in connection with make-to-order production and engineer-to-order production.

There aretwo alternative processes:

  • using thespecial procurement keyDirect procurement

This process is like the direct production process.

  • using theitem categoryNon-stock item.

We recommend the process using the special procurement key.

Prerequisites

  • For the plant and/or for an MRP group, we have definedwhenthe direct procurement is to be triggered. In Customizing for MRP, we have set the indicator in theDirect procurementfield of the IMG activitySettings for direct procurementas follows:
  • Indicator1or3(these are identical), if direct procurement is to be triggered during MRP
  • Indicator2orblank(these are identical), if direct procurement is only to be triggered after the conversion or creation of a production order.

Process Using the Special Procurement Key for Direct Procurement

  • We have set the item typestock itemfor the components in the BOM, which are to be procured directly.
  • If we want to use direct procurementfor a particular componentall the time, we have entered the special procurement key for direct procurement in the material master for the component (MRP 2view).
  • If we want to use direct procurementfor a particular BOMonly, we have entered the special procurement key for direct procurement in the corresponding BOM item in theMRP data This entry overwrites the entry in the material master.

Note

If we have activated direct procurement in the material master, we can switch off direct procurement for a particular BOM, if we deactivate direct procurement in theMRP dataarea of the corresponding BOM item underExplosion type. This entry overwrites the entry in the material master.

Process Using the Item Category for Non-Stock Item.

  • We have set the item typenon-stock itemfor the components in the BOM that are to be procured directly. We have also entered an item number and a detailed long text for the BOM item.

This is the only possible process for materials without a material master.

Features

The system automatically triggers direct procurement at the selected time.

  • In the planning run, the system does not create dependent requirements formaterials without a material master, but does create purchase requisitions directly for them. The system thereby copies the BOM long text into the purchase requisition. The system does not display the materials in the MRP list or stock/requirement list, because they do not have a material number and the system can only display materials with material numbers in these lists.

Note

We set the copying of the long text for the BOM item in Customizing for Purchasing in the IMG activityDefine text types and copying rules.

  • Formaterials with a material master, MRP creates dependent requirements and (according to the creation indicator for the planning run) planned orders for direct procurement or purchase requisitions for direct procurement. The system displays these in a separatedirect procurement segmentin the MRP list and the stock/requirements list.
  • When the planned order for the finished product is converted into a production order, all planned orders for subordinate components that are to be procured directly are automatically converted into purchase requisitions.
  • The system adapts planned orders for direct procurement and purchase requisitions for direct procurement to changes in date and quantity of the superior assembly, even if they are firmed, so that inconsistencies in planning are avoided. Manual changes are reversed.

Whenfirmed purchase requisitions for direct procurement are changed, the system automatically sends the buyer amailwith the data for the change

Caution

We can only make restricted changes to purchase requisitions for direct procurement. Changes to quantities and dates are not possible.

Material requirements planning is usually carried out at plant level. This means that the system calculates the plant stock (except for individual sales order stocks) as the total of the stocks at the individual storage locations. It may be necessary to exclude storage location stock from the plant’s MRP run, or we may want to plan certain stocks separately.

Example

  • A warehouse is geographically too far away from the production location that is planned with the storage location MRP.
  • The stock of a storage location is only available for service and not for production.

Integration

If we plan several storage locations together or also want to plan storage locations using MRP, we can plan with MRP Area

Key Features

The following options are available:

  • The storage location is to beplanned separately. Fundamentally, separate storage location MRP is carried out using consumption-based planning . In this case, we must also define areorder leveland areplenishment quantity(fixed lot size) at storage location level. In so doing, it is possible to monitor this storage location’s stock automatically, and if the stock level should fall below the reorder level the storage location is also replenished automatically.

In the planning run, stock that lies in this storage location, and which is planned separately, is not contained in the available stock at plant level.

If a receipt element (planned order, purchase requisition, purchase order, production order, and so on) or an issue element (reservation, sales order) refers to either a storage location that is excluded from the planning run or one that is planned separately these elements are not taken into account at plant level.

Reservations and sales orders, which are planned in a storage location for which MRP is carried out separately, are not included when calculating plant stock. The net requirements calculation for these requirements is restricted to this storage location.

  • The storage location isexcluded from the planning run. In this case, the storage location’s stock is not contained in the available stock at plant level, nor is it included in the planning run. The exclusion of storage location stock is only relevant to the planning run. We can, however, still make withdrawals from this stock.

in second Part will talk about

Planning with MRP areas

Multi-plant/site planning

Requirements grouping for individual project planning

Please share, Like and Comment anything else you want to share or add points.

Thanks & Regards

Ruthvik Chowdary

SME – S/4 HANA Manufacturing & Procurement

SAP Ariba P2P

MRP Planning Process | SAP Blogs (2024)

FAQs

What are the 4 steps of MRP? ›

MRP steps include identifying requirements, checking inventory, scheduling production, and identifying issues.

How do I run MRP step by step? ›

Procedure
  1. To start MRP wizard, choose MRP MRP Wizard.
  2. Create a new MRP scenario or select an existing one. ...
  3. Define the parameters for your scenario, such as the planning horizon and item details, and choose your display preferences. ...
  4. Define the data sources for requirements that you want to include in your MRP scenario.

What are the methods of MRP planning? ›

Material requirements planning (MRP) is a system for calculating the materials and components needed to manufacture a product. It consists of three primary steps: taking inventory of the materials and components on hand, identifying which additional ones are needed and then scheduling their production or purchase.

What is the MRP process? ›

Definition of MRP

MRP is a system designed to plan manufacturing production. It identifies necessary materials, estimates quantities, determines when materials will be required to meet the production schedule, and manages delivery timing – with the goal of meeting demands and improving overall productivity.

What are the 8 features of the MRP system? ›

Here are the top 8 benefits of MRP systems.
  • Inventory control. Inventory management is crucial to realising manufacturing efficiency. ...
  • Purchase planning. ...
  • Production planning. ...
  • Work scheduling. ...
  • Resource management. ...
  • Data management and documentation. ...
  • Economic purchasing. ...
  • Time-saving.
Jan 23, 2019

How do I make a MRP planning schedule? ›

Gross Requirements (GR): You generate this MRP calculation through forecast scheduling using the number of produced units, the amount of required material for each produced unit, the current stock, and the ordered stock /stock in transit. This is the total demand for an item during a specific time period.

What are the processing keys in MRP? ›

This setting is the main indicator for which the MRP planning run will execute. There are three processing keys to choose from are net change planning (NETCH), net change planning in the planning horizon (NETPL), and online regenerative planning (NEUPL).

Is SAP an MRP system? ›

Conclusion. SAP is an ERP (Enterprise Resource Planning) system, not an MRP (Material Requirements Planning) system. While SAP offers modules that cover various aspects of business operations, it is not specifically focused on manufacturing and production planning like an MRP system.

What is the planning horizon in MRP? ›

Planning horizon is the Time period in days, MRP will consider the requirements for Planning. We can define this in number of days in OPPQ and/or in OPPR. Simply it is = Cumulative lead time + Longest batching period.

What is a planned order in MRP? ›

A firm MRP planned order represents a planned replenishment that is "firmed" using the Planner Workbench for MRP planned items. This allows the planner to stabilize portions of the MRP without creating discrete jobs or purchase requisitions.

What is the formula for calculating MRP? ›

Maximum Retail Price = Product's actual Cost + Profit Margin + CnF margin + Distributor Margin + Retailer Margin + GST + Transportation + other expenses etc. “maximum retail price” means such price at which the product shall be sold in retail and such price shall include all taxes levied on the product.”

What are the three inputs for every MRP system? ›

The three basic inputs of an MRP system are the Master Production Schedule (MPS), Inventory Status File (ISF) and Bill of Materials (BOM). The MPS is simply the quantity and timing of all end goods to be produced over a specific time period. MPS is estimated through customer orders and demand forecasts.

What is an example of material resource planning? ›

Material resource planning example is the manufacturing process where bulk products are produced like chemicals. In this, the product cannot be broken down into their constituent parts. The examples of best resource management tools are xTuple, Sinnaps, IQMS MRP, abas ERP, and Prodsmart.

What are the orders in MRP? ›

It has two types of order: one pre-set in the item unit as subcontract and the other determined as subcontract for capacity reason after the manufacturing planning. The former is usually called Item Subcontract, and the latter is called Process Subcontract.

What are the MRP types? ›

The various MRP types include ND, PD,P1,P2 and others. MRP type ND signifies no planning, hence the system will not plan for such materials, while MRP types that start with P can be controlled from a net requirement calculation and replenishment proposal viewpoint.

What are the three basic components of a material requirements planning MRP system? ›

Those are the master production schedule, bills of materials, and the inventory status records. They might go by slightly different names depending on the system, but they should be easy to identify. In plain language, they keep track of what you need to make, what it takes to make it, and what you have on hand.

What is the MRP process of calculating materials requirements? ›

MRP consists of three basic steps: Identifying the Quantity Requirements: Determine what quantity is on hand, in an open purchase order, planned for manufacturing, already committed to existing orders, and forecasted. These requirements are specific to each company and each company location and change with the date.

Top Articles
Latest Posts
Article information

Author: Greg Kuvalis

Last Updated:

Views: 6014

Rating: 4.4 / 5 (75 voted)

Reviews: 90% of readers found this page helpful

Author information

Name: Greg Kuvalis

Birthday: 1996-12-20

Address: 53157 Trantow Inlet, Townemouth, FL 92564-0267

Phone: +68218650356656

Job: IT Representative

Hobby: Knitting, Amateur radio, Skiing, Running, Mountain biking, Slacklining, Electronics

Introduction: My name is Greg Kuvalis, I am a witty, spotless, beautiful, charming, delightful, thankful, beautiful person who loves writing and wants to share my knowledge and understanding with you.