[Solved] In PERT analysis, a critical activity has: (2024)

Explanation:

Critical activity:

Critical activitiesare those activities whosefloat is zeroand they lie on thecritical path.

Float:

Relax or delay provided to any activity is known as float.

Floats are of three types. They are as follows:

[Solved] In PERT analysis, a critical activity has: (1)

Total Float (TF):

The maximum delay or relax provided to any activity without affecting the project duration.

TF = Lj– Ei– dij

Free Float (FF):

Relax or delay provided to any activity without affecting theEarliest Start Time (EST)of the successor activity.

FF = Ej– Ei– dij

Independent Float:

Relax or delay provided to any activity without affecting the Earliest Start Time(EST)of successoractivity as well as Latest Finish Time(LFT)of the predecessoractivity.

IF = Ej– Li- dij

Relation among floatTF ≥ FF ≥ IF

[Solved] In PERT analysis, a critical activity has: (2)Important Points

Critical Path:

  • Thelongest pathin the network diagram is calledCritical Path.
  • Thelengthof the Critical Path determines theminimum durationrequired for the completion of the project.
[Solved] In PERT analysis, a critical activity has: (2024)
Top Articles
Latest Posts
Article information

Author: Greg Kuvalis

Last Updated:

Views: 6703

Rating: 4.4 / 5 (75 voted)

Reviews: 82% of readers found this page helpful

Author information

Name: Greg Kuvalis

Birthday: 1996-12-20

Address: 53157 Trantow Inlet, Townemouth, FL 92564-0267

Phone: +68218650356656

Job: IT Representative

Hobby: Knitting, Amateur radio, Skiing, Running, Mountain biking, Slacklining, Electronics

Introduction: My name is Greg Kuvalis, I am a witty, spotless, beautiful, charming, delightful, thankful, beautiful person who loves writing and wants to share my knowledge and understanding with you.