PERT and CPM Question 1:

In PERT chart, the activity time distribution is

  1. Normal
  2. Binomial
  3. Poisson
  4. Beta

Answer (Detailed Solution Below)

Option 4 : Beta

India's Super Teachers for all govt. exams Under One RoofFREE Demo Classes Available*Enroll For Free Now

PERT and CPM Question 1 Detailed Solution

The correct answer is Beta.

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (3)Key PointsIn PERT charts, the activity time distribution is assumed to follow a Beta distribution.

Here's why the Beta distribution is used:

Uncertainty: Unlike Critical Path Method (CPM), PERT acknowledges the uncertainty associated with activity durations in projects. The Beta distribution allows for incorporating this uncertainty by capturing a range of possible durations for each activity.
Flexibility: The beta distribution is a flexible probability distribution with parameters that can be adjusted to reflect the specific characteristics of an activity, including its optimistic, pessimistic, and most likely durations. This allows for a more realistic representation of the possible timeframes for an activity compared to assuming a fixed duration.
Shape: The beta distribution can take on various shapes depending on the chosen parameters, allowing it to model different scenarios, such as activities with skewed distributions or durations concentrated around the most likely time.
Therefore, the Beta distribution provides a suitable framework for representing the inherent uncertainty and variability in activity durations within a PERT chart

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (4)

Daily Live MasterClasses

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (5)

Practice Question Bank

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (6)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

PERT and CPM Question 2:

The expected return of ABC stocks calculated using CAPM is 15.5%. The risk free rate is 3.5% and the beta of the stock is 1.2. Calculate the implied market risk premium (i.e. Rm – Rf).

  1. 5.5%
  2. 6.5%
  3. 10.0%
  4. 15.5%

Answer (Detailed Solution Below)

Option 3 : 10.0%

PERT and CPM Question 2 Detailed Solution

The correct answer is10.0%.

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (7)Key Points

  • TheCAPM modelcalculatesexpected returns from an investmentand can be used to determine prices for individual securities.
  • The Capital Asset Pricing Model (CAPM) was developed in the early 1960s by William Sharpe, Jack Treynor, John Lintner and Jan Mossin.
  • The formula to calculate expected return usingCAPM model:

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (8)

It is given that E(R) = 15.5%, Rf = 3.5%, beta = 1.2

So, 15.5 = 3.5 + 1.2 (Rm - Rf)

15.5 - 3.5 = 1.2 (Rm - Rf)

12 = 1.2 (Rm - Rf)

So Rm - Rf = 12 / 1.2

= 10

Hence, the correct answer is10.0%.

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (9)

Daily Live MasterClasses

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (10)

Practice Question Bank

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (11)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

PERT and CPM Question 3:

Critical path method is good for

  1. Small project only
  2. Large project only
  3. Both small and large projects equally
  4. Neither small nor large projects

Answer (Detailed Solution Below)

Option 2 : Large project only

PERT and CPM Question 3 Detailed Solution

The correct answer is Larger projects only.

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (12)Key PointsThe Critical path method consists of a sequence of events that has to be completed before the completion of the project. It shows the longest sequence of events or tasks that have to be completed in the project duration. So, it is suitable for larger and complex projects only.

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (13)Important Points

Critical Path Method (CPM):

The critical path method is used by the project managers indeveloping the project schedule.This is done using anetwork diagram which shows the sequence of events in a project. This is prepared during theplanning phase of the projectso that project managers can focus on project cost, resources, and time beforehand.

Importance of Critical Path Method (CPM):

  • It helps to identify theproject dependencies, risks, and resource constraints. Through the network diagram, the project managers can identify such problems and resolve them before they occur.
  • It helps in estimating the accurateproject timings.
  • It helps the managers identify thecritical tasksthat need attention.
  • It helps in monitoring theproject's progress and measuring the variance.

Hence, the correct answer is larger projects only.

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (14)

Daily Live MasterClasses

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (15)

Practice Question Bank

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (16)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

PERT and CPM Question 4:

PERT is used in the preparation of :

  1. Budgeting
  2. Scheduling
  3. Evaluating
  4. Finalizing

Answer (Detailed Solution Below)

Option 2 : Scheduling

PERT and CPM Question 4 Detailed Solution

The correct answer is Scheduling.

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (17)Key PointsActivity Definition:

PERT begins with breaking down the project into specific activities or tasks. Each task is identified and defined clearly. Activities should be well-defined and have a specific start and end point.
Activity Sequencing:

Once activities are identified, the next step is to establish the relationships and dependencies between them. This involves determining the order in which activities must be performed and identifying any constraints or dependencies between tasks.
Time Estimation:

Time estimation involves estimating the time required to complete each activity. PERT uses three time estimates for each activity: optimistic time (the minimum time required), pessimistic time (the maximum time required), and most likely time (the best estimate based on realistic conditions).
Critical Path Analysis:

Critical path analysis is a key aspect of PERT. The critical path is the longest sequence of dependent activities that must be completed on time to ensure that the project is completed within the specified timeframe. Activities on the critical path have zero slack or float, meaning any delay in these activities will directly impact the project's overall timeline.
Float or Slack:

Float or slack is the amount of time that a task can be delayed without delaying the project's completion date. Non-critical activities have float, providing some flexibility in scheduling

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (18)

Daily Live MasterClasses

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (19)

Practice Question Bank

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (20)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

PERT and CPM Question 5:

Playing Float is a concept used in

  1. Cash Management
  2. Inventory Management
  3. Receivables Management
  4. All of These

Answer (Detailed Solution Below)

Option 4 : All of These

PERT and CPM Question 5 Detailed Solution

The correct answer isAll of These.

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (21)Key Points

Playing float is a concept that can be used in all three of the areas you mentioned: cash management, receivable management, and inventory management.

Cash management is the process of managing a company's cash flow. Playing float can be used to improve cash flow by delaying the payment of bills or by accelerating the collection of receivables.

Receivable management is the process of managing a company's accounts receivable. Playing float can be used to accelerate the collection of receivables by mailing checks early or by offering discounts for early payment.

Inventory management is the process of managing a company's inventory levels. Playing float can be used to reduce inventory levels by delaying the purchase of materials or by selling products before they are received.

Here are some specific examples of how playing float can be used in each of these areas:

Cash management: A company can delay the payment of bills by mailing checks late or by negotiating longer payment terms with its suppliers. This can free up cash that can be used for other purposes.

Receivable management: A company can accelerate the collection of receivables by offering discounts for early payment. This can encourage customers to pay their bills sooner, which can improve the company's cash flow.

Inventory management: A company can reduce inventory levels by delaying the purchase of materials or by selling products before they are received. For example, a company could wait until it has received an order for a product before purchasing the materials to produce it.

Playing float can be a useful tool for improving cash flow and reducing costs. However, it is important to use it responsibly. If a company abuses float, it could damage its relationships with its suppliers, customers, and creditors

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (22)

Daily Live MasterClasses

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (23)

Practice Question Bank

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (24)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

Top PERT and CPM MCQ Objective Questions

PERT and CPM Question 6

Download Solution PDF

A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is

  1. 3
  2. 9
  3. 81
  4. 27

Answer (Detailed Solution Below)

Option 2 : 9

PERT and CPM Question 6 Detailed Solution

Download Solution PDF

Concept:

In CPM:

The standard deviation of critical path:

σcp=\(\sqrt {Sum\;of\;variance\;along\;critical\;path} \)

σcp =\(\sqrt {σ _1^2 + σ _2^2 + \ldots + σ _8^2 + σ _9^2} \)

Where,σ12, ....,σ89are the standard deviation of each activity on the critical path

Calculation:

Given:

σ12, ....,σ89= 3

σcp=\(\sqrt {σ _1^2 + σ _2^2 + \ldots + σ _8^2 + σ _9^2} \)

σcp =\(\sqrt {3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2} \)

σcp =\(\sqrt {9 \times 9} \)= 9

∴ the standard deviation of the critical path is9.

Download Solution PDFShare on Whatsapp

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (25)

Daily Live MasterClasses

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (26)

Practice Question Bank

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (27)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

PERT and CPM Question 7

Download Solution PDF

Pessimistic time and optimistic time of completion of an activity are given as 10 days and 4 days respectively, the variance of the activity will be

  1. 1
  2. 6
  3. 12
  4. 18

Answer (Detailed Solution Below)

Option 1 : 1

PERT and CPM Question 7 Detailed Solution

Download Solution PDF

Concept:

Project Evaluation and Review Technique (PERT) is probabilistic in nature and is based upon three-time estimates to complete an activity.

Optimistic Time (to):It is the minimum time that will be taken to complete an activity if everything goes according to the plan.

Pessimistic Time (tp):It is the maximum time that will be taken to complete an activity when everything goes against the plan.

Most likely time (tm):It is the time required to complete a project when an activity is executed under normal conditions.

Average or most expected time is given by\({t_E} = \left( {\frac{{{t_p}\; + \;4{t_m}\; + {t_o}}}{6}} \right)\)

The variance gives the measure of uncertainty of activity completion. The variance of the activity is given by

Variance,\(V = {\left( {\frac{{{t_p} - {t_0}}}{6}} \right)^2}\)

Standard duration,\(\sigma = \sqrt {variance} \)

Calculation:

Given:

tp = 10 days, to = 4 days

\({\rm{V}} = {\left( {\frac{{{{\rm{t}}_{\rm{p}}} - {{\rm{t}}_{\rm{o}}}}}{6}} \right)^2} = {\left( {\frac{{10 - 4}}{6}} \right)^2} = 1\)

The variance of the activity is 1.

Download Solution PDFShare on Whatsapp

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (28)

Daily Live MasterClasses

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (29)

Practice Question Bank

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (30)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

PERT and CPM Question 8

Download Solution PDF

In PERT chart, the activity time distribution is

  1. Normal
  2. Binomial
  3. Poisson
  4. Beta

Answer (Detailed Solution Below)

Option 4 : Beta

PERT and CPM Question 8 Detailed Solution

Download Solution PDF

Explanation:

CPM does not directly model uncertainty.

PERT was developed to address the needs of projects which are being done for the first time – a challenge to estimate activity duration.

PERT (Program Evaluation and Review Technique) uses 3 cases:

  • Most Optimistic
  • Most Pessimistic
  • Most likely durations

PERT determines the probability for each duration, whereas CPM considers the most likely duration.

In the standard PERT analysis, the distribution assumed for the activity times is a Beta distribution.

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (31)

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (32)

Download Solution PDFShare on Whatsapp

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (33)

Daily Live MasterClasses

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (34)

Practice Question Bank

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (35)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

PERT and CPM Question 9

Download Solution PDF

Which among the following uses probabilistic time estimates for project management?

  1. CPM
  2. Gantt chart
  3. PERT
  4. OC curve

Answer (Detailed Solution Below)

Option 3 : PERT

PERT and CPM Question 9 Detailed Solution

Download Solution PDF

Explanation:

PERT stands for Program Evaluation and Review Technique and was developed to address the needs of projects for which the time and cost estimates tend to be quite uncertain.

It has a probabilistic approach and hence suitable for the projects which are to be conducted for the first time or projects related toresearch and development.

PERT uses 3 cases:

  • Optimistic timeestimates the shortest possible time required for the completion of the activity.
  • Most likely timeestimates the time required for the completion of activity under normal circ*mstances.
  • Pessimistic timeestimates the longest possible time required for the completion of the activity.

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (36)

Download Solution PDFShare on Whatsapp

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (37)

Daily Live MasterClasses

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (38)

Practice Question Bank

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (39)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

PERT and CPM Question 10

Download Solution PDF

Critical path method is good for

  1. small project only
  2. large project only
  3. both small and large projects equally
  4. neither small nor large projects

Answer (Detailed Solution Below)

Option 2 : large project only

PERT and CPM Question 10 Detailed Solution

Download Solution PDF

Explanation:

Critical Path:

Acritical pathis a sequence of interdependent activities or tasks that must be finished before the project can be finished. It is thelongest path (i.e. path with the longest duration) from project start to finish.

Critical Path Method:

  • Thecritical path method (CPM)is a project modeling technique that’s used by project managers to find importantdeadlinesand deliver a project on time.
  • In a project, the critical path is thelongest distancebetween the start and the finish, including all the tasks and their duration.
  • Once a critical path is determined, you’ll have aclear pictureof the project’s actual schedule.
  • To find this, project managers use theCPM algorithmto find theleast amountof time necessary to complete each task with the least amount of slack.
  • For small projects, managers are often able to memorize and to coordinate all of the various tasks necessary for their completion.
  • For larger projects, however, with numerous activities occurring simultaneously, remembering and coordinating these activities can prove much more difficult. CPM and related tools allow managers to determine which particular tasks most affect the total time of the project and enable managers to better schedule each task so that deadlines are met at the least possible cost
Download Solution PDFShare on Whatsapp

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (40)

Daily Live MasterClasses

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (41)

Practice Question Bank

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (42)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

PERT and CPM Question 11

Download Solution PDF

The path which moves along the activities having total float zero, in the network diagram is called

  1. Free Float
  2. Critical Path
  3. Total Float
  4. Independent Float

Answer (Detailed Solution Below)

Option 2 : Critical Path

PERT and CPM Question 11 Detailed Solution

Download Solution PDF

Explanation :

Acritical path is a sequence of interdependent activities or tasks that must be finished before the project can be finished. It is the longest path (i.e. path with the longest duration) from project start to finish.

The path which moves along the activities having total float zero.

A. Critical Path Method
1. The critical path method (CPM) is a project modelling technique that's used by project managers to find important deadlines and deliver a project on time.

2. In a project, the critical path is the longest distance between the start and the finish, including all the tasks and their duration.

3. Once a critical path is determined, you'll have a clear picture of the project's actual schedule.

4. To find this, project managers use the CPM algorithm to find the least amount of time necessary to complete each task with the least amount of slack.
5. Once done by hand, nowadays, the critical path is calculated automatically by the project scheduling software. That makes the whole method a lot easier.

B. Critical Path Analysis
1. As mentioned, the purpose of a critical path is to find the least amount of time you'll need to complete a task.

2. Critical path analysis furthers your ability to make better estimates for scheduling because you're mapping out every important task that must be done for a successful project.

C. Critical Path Example

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (43)

Download Solution PDFShare on Whatsapp

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (44)

Daily Live MasterClasses

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (45)

Practice Question Bank

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (46)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

PERT and CPM Question 12

Download Solution PDF

The amount of time by which an activity can be delayed without affecting project completion time is

  1. Free float
  2. Total float
  3. Independent float
  4. Activity float

Answer (Detailed Solution Below)

Option 2 : Total float

PERT and CPM Question 12 Detailed Solution

Download Solution PDF

Explanation

Slack or Event Float

  • Slack corresponds to theevent in PERT.
  • Float corresponds to activity in CPM.

Slack

  • It is defined as the amount of time by which an event can be delayed without delaying the project schedule.
  • Slack of an event = Latest Start Time – Earliest Start Time OR Latest Finish Time – Earliest Finish Time

There are three types of floats.

Total Float (TF)

  • It is the amount of time by which an activity can be delayed without delaying the project duration.
  • Extra time available for an activity without delaying the project schedule.
  • If the value of TF is,
    • Positive– Recourses aresurplusand can be allocated for other activities.
    • Zero– Resources arejust sufficientto complete the activity on time.
    • Negative– Resourcesare not sufficientand activity may not complete
  • Total Float = Latest start time – Earliest start time

Free Float (FF)

· Part of the Total Float, which can be used without affecting the float of succeeding activity.

· Extra time by which an activity can be delayed so that thesucceeding activity can be started on earliest start time.

  • Free float = Total Float – Head event slack

Independent Float

(IF)

  • It is amount of free float time which can be used without affectingeither the head or the tail event.
  • Independent float = free Float – Tail event slack
Download Solution PDFShare on Whatsapp

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (47)

Daily Live MasterClasses

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (48)

Practice Question Bank

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (49)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

PERT and CPM Question 13

Download Solution PDF

In construction project planning, free float can affect which of the following?

  1. Only that particular activity
  2. Succeeding activity
  3. Overall completion
  4. Preceding activity

Answer (Detailed Solution Below)

Option 4 : Preceding activity

PERT and CPM Question 13 Detailed Solution

Download Solution PDF

Concept

Free float is the portion of total float by which an activity can be delayed without affecting succeeding activity.

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (50)

\({F_F} = \left( {T_E^j - T_E^i} \right) - tij\)

Free float is also equal to total float minus head event slack.

\({F_F} = {F_T} - S_j\)

In free float, the preceding activity is not allowed to occur at its latest time and hence total float of the preceding activity is affected. However, the succeeding activity can start at its earliest start time, so its total float is unaffected.

Total Float: It is the maximum delay possible for an activity without considering any delay in itsprecedence or succeeding activity.

Independent float is the maximum delay possible for an activity which used floats of preceding activity, but we will not affect the float of succeeding activity.

Download Solution PDFShare on Whatsapp

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (51)

Daily Live MasterClasses

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (52)

Practice Question Bank

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (53)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

PERT and CPM Question 14

Download Solution PDF

Which of the following statements is not correct about PERT ?

  1. Network is constructed based on the events.
  2. It does not take uncertainties involved in the estimation of times.
  3. Network deals with uncertainties and hence three time estimations are considered.
  4. As there is no certainty of time, activity duration cannot be reduced.

Answer (Detailed Solution Below)

Option 2 : It does not take uncertainties involved in the estimation of times.

PERT and CPM Question 14 Detailed Solution

Download Solution PDF

Explanation:

PERT stands for "ProgramEvaluation and Review Technique". This network model is used for project scheduling.

Difference between PERT and CPM (Critical Path Method)

PERT

CPM

1.Probabilistic approach

1.Deterministic approach

2. Three-time estimate

2. One-time estimate

3.Event oriented network model

3.Activity-oriented network model

4. The slack concept is used

4. Float concept is used

5. Project crashing is not possible

5.Project crashing is possible

6. Deals with probabilistic time estimates.

6.Deals with deterministic time estimates.

PERT does take uncertainties involved in the estimation of times, therefore three-time estimates have been taken for the calculation project duration. They are optimistic (to), pessimistic (tp), and most likely (tm).

\(T_e=\frac{t_o\;+\;4t_m\;+\;t_p}{6}\)

Therefore, the option 2is the incorrect statement among the given options.

Download Solution PDFShare on Whatsapp

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (54)

Daily Live MasterClasses

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (55)

Practice Question Bank

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (56)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

PERT and CPM Question 15

Download Solution PDF

Consider the following network of activities, with each activity named A-L, illustrated in the nodes of the network.

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (57)

The number of hours required for each activity is shown alongside the nodes. The slack on the activity L, is _____ hours.

Answer (Detailed Solution Below) 2

PERT and CPM Question 15 Detailed Solution

Download Solution PDF

Concept:

This is a case of activity on node network system (AON).

Slack = latest finish time – Earliest finish time

Calculation:

Slack = latest finish time – Earliest finish time

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (58)

Slack on Activity L = 42 – 40 = 2

Important Points:-

1.AON network system enables efficient scheduling and controlling.

2. AON network system eliminates the use of dummies thus logical relationship is established by using arrows.

Download Solution PDFShare on Whatsapp

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (59)

Daily Live MasterClasses

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (60)

Practice Question Bank

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (61)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

[Solved] PERT and CPM MCQ [Free PDF] - Objective Question Answer for PERT and CPM Quiz - Download Now! (2024)
Top Articles
Latest Posts
Article information

Author: Rob Wisoky

Last Updated:

Views: 5834

Rating: 4.8 / 5 (68 voted)

Reviews: 91% of readers found this page helpful

Author information

Name: Rob Wisoky

Birthday: 1994-09-30

Address: 5789 Michel Vista, West Domenic, OR 80464-9452

Phone: +97313824072371

Job: Education Orchestrator

Hobby: Lockpicking, Crocheting, Baton twirling, Video gaming, Jogging, Whittling, Model building

Introduction: My name is Rob Wisoky, I am a smiling, helpful, encouraging, zealous, energetic, faithful, fantastic person who loves writing and wants to share my knowledge and understanding with you.