8.3 Critical Path and Float – Project Management from Simple to Complex (2024)

Learning Objective

  1. Calculate critical path, project float, early start dates, and late start dates.

The critical path is the path through the network that results in the latest completion date of the project.

If any activity on the critical path is delayed, the completion of the project will be delayed by an equal amount. It is the path with the greatest total duration. To determine the critical path, add the amount of time estimated for the duration of each activity to the previous activity to determine which path through the network has the longest total duration, as shown in Figure 8.15 “Critical Path”. Durations are indicated in days. The critical path through these tasks takes at least eight days. Activities on the critical path are shaded.

Figure 8.15 Critical Path

Early Start Dates

Starting dates can be assigned to each activity by doing a forward pass proceeding from left to right in the network diagram beginning with the project start date. The dates derived by this method are the early start (ES) dates. The early start date for an activity is the earliest date the activity can begin. The estimate considers durations and resource availability calendars. To calculate early start dates, begin with the project start date and assign that date as the start date of activities that have no predecessor activities. Follow these steps to calculate the early start dates of subsequent activities, assuming finish-start relationships:

  • Add the predecessor activity’s duration to its start date.
  • Add the lag time or subtract the lead time.
  • Refer to the resource calendar (or calendars) that applies to the people and equipment necessary for the activity, and add the number of off-days that the activity would span on those calendars.
  • Assign the calculated date as the early start date of the successor activity.

Forward Pass for John’s Move

John begins planning his move to Atlanta the same day he accepts the job. The start date in this example is Monday, November 29, 2010. Tasks 1.1 and 2.1 can both start on that day, so the early start dates for tasks 1.1 and 2.1 are November 29. John calculates the early start date for the activities. A partial list is provided below. Compare the figure below and the figure in the next sidebar. Observe that John is willing to work on weekends, but activity 2.2.3 is delayed by two days because one of the moving companies did not provide bids on the weekend. Observe that activity 2.3 has a lead time of one day, but that relationship is between activity 2.1 and 2.3. The network path from activity 1.3 is longer, so the lead time with activity 2.1 is not considered in calculating the early start date of 2.3.

Figure 8.16 Early Start Dates Determined by a Forward Pass

CodeDescriptionPredecessorsRelationshipsLead/LagResourcesDurationEarly Start Date
1aContact Dion and CarlitaNone0J,D,C
.25 hr each
2 d11/29
1bHost planning lunch1aFS
(Finish/Start)
0J,D,C
2 hr each
1 d12/1
1cDevelop and distribute schedule1bFS0J 2 hr1 d12/2
1dMake hotel arrangement in Atlanta1aFS0J .5 hr1 d11/30
2aGather packing materialNone0D 2 hr1 d11/29
2biContact van companies and get 3 bids1cFS2 d12/3
2bii2biFS0J .5 hr1 d12/7
2biiiSign moving contract2biiFS1 d12/8
2cPack small and delicate items1c
2a
FS
FS
-1C 6 hr1 d12/3

Doing this process manually is error prone and time consuming. Fortunately, there are computer programs to assist in the process, but the project manager must understand the process well enough to recognize computer errors. Computer software must be combined with common sense or good judgment.

Float

Float, sometimes called slack, is the amount of time an activity, network path, or project can be delayed from the early start without changing the completion date of the project.

Total Float

Total float is the difference between the finish date of the last activity on the critical path and the project completion date. Any delay in an activity on the critical path would reduce the amount of total float available on the project. A project can also have negative float, which means the calculated completion date of the last activity is later than the targeted completion date established at the beginning of the project.

Float in John’s Move

The last activity in John’s move has an early start date of December 28 and a duration of one day. John could start work on Wednesday, December 29. John’s first day at work is Monday, January 3, so the project has a total float of five days.

Figure 8.17 Total Project Float

Late Start Dates

The next step is to work through the network diagram from right to left beginning with the mandated completion date, which is a milestone that is set in the project plan. Subtract the duration of each activity in each path to determine the latest date the activity could begin and still meet the project completion date. Resource calendars must be considered in the backward pass as well as the forward pass.

To calculate late start dates, begin with the project completion milestone and assign that date as the finish date of its predecessor activities. Follow these steps to calculate the late start dates of predecessor activities, assuming finish-start relationships:

  • Subtract the predecessor activity’s duration from its late finish date.
  • Subtract the lag time or add the lead time to the late finish date.
  • Refer to the resource calendar (or calendars) that applies to the people and equipment necessary for the activity, and subtract the number of off days that the activity would span on those calendars.
  • Assign the calculated date as the late start date of the predecessor activity.

The difference between the early start date and the late start date for activities on the critical path is usually the same as the total float, unless the activities are affected by the resource calendars differently in the forward and backward pass. For example, if a piece of key equipment is only available for a few days, activities that depend on it have the same start and finish dates in the forward and backward passes.

Free Float

If activities that are not on the critical path have a difference between their early start date and their late start date, those activities can be delayed without affecting the project completion date. The float on those activities is called free float.

Key Takeaway

  • To calculate total project float, begin at the start date and add the duration of each activity in each possible path through the network diagram, including nonworking days from the resource calendars, to determine the early project end date. The longest path through the network is the critical path. The difference between the early end date and the required completion date of the project is the total project float, and the start date of each activity is the early start date. To calculate the late start dates, begin with the required project completion date and work backward, subtracting the duration of each activity through each possible pathway.

Exercises

  1. The path through the network diagram that has the longest total duration is the __________ path.
  2. The difference between the sum of the activity durations along the critical path and the project completion date is the project _______.
  3. If two sequential activities overlap and the successor activity can begin three days before the predecessor begins, those three days are called _________ time.
  4. If the last activity in the critical path has a completion date that is five days later than the project completion date, the project has a _______ _________ (two words) of five days.
  5. What is the difference between free float and project float?
  6. If an activity has a duration of three days, how do you calculate the finish date in a way that considers availability of the resources for that activity?
  7. What would be an example of lag time between two activities?

Project Float

Consider a project in which you have been involved that experienced unexpected delays. Describe how the project’s manager dealt with the delays. Specifically, consider if the delay was due to an activity that was on the project’s critical path, if people or resources were diverted from other tasks, or if free float existed in the original schedule. Describe the ultimate effect on the project’s completion date.

8.3 Critical Path and Float – Project Management from Simple to Complex (2024)

FAQs

What is critical path and float in project management? ›

Any activity or task on the critical path has zero float. That is, you can't delay it at all without causing a delay in the project or dependent tasks. However, there are plenty of other activities in the project that can be delayed. The quantification of this delay is called the “float”.

What is a critical path in a project __________? ›

A critical path in project management is the longest sequence of activities that must be finished on time in order for the entire project to be complete. Any delays in critical tasks will delay the whole project.

What is the formula for float time critical path? ›

With your critical and non-critical task paths identified and planned, it's time to calculate your float. These can actually be calculated with a simple formula. To calculate total float, subtract the task's earliest finish (EF) date from its latest finish (LF) date. It looks like this: LF - EF = total float.

What is a critical path a ________ path from beginning to the end of a project? ›

The time required to traverse each path is the sum of the times associated with all jobs on the path. The critical path (or paths) is the longest path (in time) from Start to Finish; it indicates the minimum time necessary to complete the entire project.

What is total float and critical path? ›

Total float is the difference between the finish date of the last activity on the critical path and the project completion date. Any delay in an activity on the critical path would reduce the amount of total float available on the project.

What is critical path in project management with example? ›

Once you — or your work management software — have listed all the paths and strings, you need to identify the longest path through the project from start to finish. So, if you've got a string of tasks that takes eight days, one that takes six days, and another that takes 12, then the 12-day string is the critical path.

What is the critical path in simple words? ›

The critical path is the longest path from the start to the end of the project, passing through all the essential tasks to the project's completion. In other words, the sequence of tasks determines the minimum time needed to complete the project.

What is the critical path in simple terms? ›

In project management, the critical path is the longest sequence of tasks that must be completed to execute a project. The tasks on the critical path are called critical activities because if they're delayed, the whole project completion will be delayed.

How do you identify the critical path of a project? ›

The 6 key steps to identifying a project's critical path
  1. List all project tasks. ...
  2. Set up task dependencies. ...
  3. Estimate task durations. ...
  4. Create network diagram to trace dependencies. ...
  5. Find the critical path. ...
  6. Update your critical path diagram and monitor progress.
Dec 20, 2022

What is the float value in project management? ›

In project management, float or slack is the amount of time that a task in a project network can be delayed without causing a delay to: subsequent tasks ("free float") project completion date ("total float").

What is the float of a critical activity? ›

Critical activities are those activities whose float is zero and they lie on the critical path.

What is free float in critical path method? ›

Free Float Defined

Free float only applies to activities not on the critical path; in other words, the delay is “free” of impact on other activities. Free float is about flexibility. Project Managers and those working to earn a PMP® certification know one core responsibility is knowing when the work will be done.

What is the critical path quizlet? ›

A critical path is the sequence of project network activities which add up to the longest overall duration, regardless if that longest duration has float or not. This determines the shortest time possible to complete the project. Critical Chain Method.

How is critical path determined in a project quizlet? ›

- The critical path determines the shortest time possible in which the project can be completed. - The critical path on any network should include nodes where all Earliest Start Times and the Latest Finish Times are the same.

What is one strategy for managing complex critical path challenges? ›

One effective strategy is to adjust work between teams or split features and stories. This involves redistributing tasks or breaking down larger components into smaller, manageable units that can be handled by different teams.

What is a float in project management? ›

Project float refers to the amount of time you can delay an entire project without affecting the customer, client or end user. Project managers often set an internal deadline for their team that's earlier than the date they agreed to deliver the finished project to their client.

Top Articles
Latest Posts
Article information

Author: Greg Kuvalis

Last Updated:

Views: 5942

Rating: 4.4 / 5 (75 voted)

Reviews: 82% of readers found this page helpful

Author information

Name: Greg Kuvalis

Birthday: 1996-12-20

Address: 53157 Trantow Inlet, Townemouth, FL 92564-0267

Phone: +68218650356656

Job: IT Representative

Hobby: Knitting, Amateur radio, Skiing, Running, Mountain biking, Slacklining, Electronics

Introduction: My name is Greg Kuvalis, I am a witty, spotless, beautiful, charming, delightful, thankful, beautiful person who loves writing and wants to share my knowledge and understanding with you.