[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (2024)

  • Home
  • Industrial Engineering
  • Operations Research
  • PERT and CPM
  • Critical Path
Download Critical Path MCQs Free PDF

Last updated on Jan 18, 2024

Latest Critical Path MCQ Objective Questions

Critical Path Question 1:

Which of the following statements is NOT true about critical path method (CPM)?

  1. CPM is concerned with activities.
  2. CPM is suitable for non - repetitive projects.
  3. CPM cannot be analysed statistically.
  4. CPM establishes a relationship between time and cost.

Answer (Detailed Solution Below)

Option 3 : CPM cannot be analysed statistically.

India's Super Teachers for all govt. exams Under One RoofFREE Demo Classes Available*Enroll For Free Now

Critical Path Question 1 Detailed Solution

Concept:

Critical Path Method (CPM):

  • The critical path method (CPM) is a technique where you identify tasks that are necessary for project completion and determine scheduling flexibilities. A critical path in project management is thelongest sequence of activitiesthat must be finished on time in order for the entire project to be complete. Any delays in critical tasks will delay the rest of the project.
  • CPM revolves around discovering the most important tasks in the project timeline, identifying task dependencies, and calculating task durations.
  • CPM was developed in the late 1950s as a method to resolve the issue of increased costs due to inefficient scheduling. Since then, CPM has become popular for planning projects and prioritizing tasks.

Program (Project)Evaluationand Review Technique (PERT):

  • Program Evaluation and Review Technique (PERT) is a method used to examine the tasks in a schedule and determine a Critical Path Method variation (CPM). It analyzes the time required to complete each task and its associated dependencies to determine the minimum time to complete a project.
  • It estimates the shortest possible time each activity will take, the most likely length of time, and the longest time that might be taken if the activity takes longer than expected. The US Navy developed the method in 1957 on the Polaris nuclear submarine project.

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (3)Additional Information

Difference between PERT and CPM

PERT

CPM

ProjectEvaluation andReviewTechnique

CriticalPathMethod

It is event-oriented.

It is activity-oriented.

It is associated with probabilistic activities.

It is associated with deterministic activities.

It is based upon a three-time estimate to complete an activity.

\({t_e} = \left( {\frac{{{t_o} + 4{t_m} + {t_p}}}{6}} \right)\)

Where, te= expected time to complete an activity

to= optimistic time, tm= mean time, tp= pessimistic time

It is based upon a single time estimate to complete an activity.

It usually doesn’t consider cost analysis.

It gives importance to cost analysis & crashing is done to minimize the cost of the CPM project.

Applications:Mainly used for R & D project

Applications:Mainly used for Construction project

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (4)

Daily Live MasterClasses

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (5)

Practice Question Bank

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (6)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

Critical Path Question 2:

The critical activity has:

  1. Normal float
  2. Maximum float
  3. Minimum float
  4. Zero float
  5. None of these

Answer (Detailed Solution Below)

Option 4 : Zero float

Critical Path Question 2 Detailed Solution

The activities with zero slack of head event and zero slack for the tail event, are called as critical activities.

The activities with zerofloat are called critical activities. The sequence of critical activities in a network is called the critical path.

So,the critical path, by definition, has a zero total float or delay. And the delay of one activity prolongs the duration of completion of the project.

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (7)

Daily Live MasterClasses

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (8)

Practice Question Bank

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (9)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

Critical Path Question 3:

A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is

  1. 3
  2. 9
  3. 81
  4. 27
  5. 54

Answer (Detailed Solution Below)

Option 2 : 9

Critical Path Question 3 Detailed Solution

Concept:

In CPM:

The standard deviation of critical path:

σcp=\(\sqrt {Sum\;of\;variance\;along\;critical\;path} \)

σcp =\(\sqrt {σ _1^2 + σ _2^2 + \ldots + σ _8^2 + σ _9^2} \)

Where,σ12, ....,σ89are the standard deviation of each activity on the critical path

Calculation:

Given:

σ12, ....,σ89= 3

σcp=\(\sqrt {σ _1^2 + σ _2^2 + \ldots + σ _8^2 + σ _9^2} \)

σcp =\(\sqrt {3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2} \)

σcp =\(\sqrt {9 \times 9} \)= 9

∴ the standard deviation of the critical path is9.

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (10)

Daily Live MasterClasses

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (11)

Practice Question Bank

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (12)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

Critical Path Question 4:

A PERT network has nine activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is

  1. 3
  2. 9
  3. 81
  4. 27

Answer (Detailed Solution Below)

Option 2 : 9

Critical Path Question 4 Detailed Solution

Concept:

In CPM:

The standard deviation of the critical path:

σcp=\(\sqrt {Sum\;of\;variance\;along\;critical\;path} \)

σcp=\(\sqrt {σ _1^2 + σ _2^2 + \ldots + σ _8^2 + σ _9^2} \)

Where,σ12, ....,σ89are the standard deviation of each activity on the critical path

Calculation:

Given:

σ12, ....,σ89= 3

σcp=\(\sqrt {σ _1^2 + σ _2^2 + \ldots + σ _8^2 + σ _9^2} \)

σcp=\(\sqrt {3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2} \)

σcp=\(\sqrt {9 \times 9} \)= 9

∴ the standard deviation of the critical path is9.

India’s #1 Learning Platform

Start Complete Exam Preparation

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

Critical Path Question 5:

The given table lists the project's activities, precedence relationships and duration. Find the critical path of the project.

ActivityPrecedenceDuration (in days)
P-3
Q-4
RP5
SQ5
TR, S7
UR, S5
VT2
WU10
  1. P-R-U-V
  2. P-R-T-U
  3. Q-S-T-U
  4. Q-S-U-W

Answer (Detailed Solution Below)

Option 4 : Q-S-U-W

Critical Path Question 5 Detailed Solution

Explanation:

The project activities, precedence relationships are given below:
[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (16)

From the diagram we can conclude that the critical path isQ-S-U-W.

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (17)

Daily Live MasterClasses

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (18)

Practice Question Bank

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (19)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

Top Critical Path MCQ Objective Questions

Critical Path Question 6

Download Solution PDF

A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is

  1. 3
  2. 9
  3. 81
  4. 27

Answer (Detailed Solution Below)

Option 2 : 9

Critical Path Question 6 Detailed Solution

Download Solution PDF

Concept:

In CPM:

The standard deviation of critical path:

σcp=\(\sqrt {Sum\;of\;variance\;along\;critical\;path} \)

σcp =\(\sqrt {σ _1^2 + σ _2^2 + \ldots + σ _8^2 + σ _9^2} \)

Where,σ12, ....,σ89are the standard deviation of each activity on the critical path

Calculation:

Given:

σ12, ....,σ89= 3

σcp=\(\sqrt {σ _1^2 + σ _2^2 + \ldots + σ _8^2 + σ _9^2} \)

σcp =\(\sqrt {3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2} \)

σcp =\(\sqrt {9 \times 9} \)= 9

∴ the standard deviation of the critical path is9.

Download Solution PDFShare on Whatsapp

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (20)

Daily Live MasterClasses

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (21)

Practice Question Bank

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (22)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

Critical Path Question 7

Download Solution PDF

Critical path method is good for

  1. small project only
  2. large project only
  3. both small and large projects equally
  4. neither small nor large projects

Answer (Detailed Solution Below)

Option 2 : large project only

Critical Path Question 7 Detailed Solution

Download Solution PDF

Explanation:

Critical Path:

Acritical pathis a sequence of interdependent activities or tasks that must be finished before the project can be finished. It is thelongest path (i.e. path with the longest duration) from project start to finish.

Critical Path Method:

  • Thecritical path method (CPM)is a project modeling technique that’s used by project managers to find importantdeadlinesand deliver a project on time.
  • In a project, the critical path is thelongest distancebetween the start and the finish, including all the tasks and their duration.
  • Once a critical path is determined, you’ll have aclear pictureof the project’s actual schedule.
  • To find this, project managers use theCPM algorithmto find theleast amountof time necessary to complete each task with the least amount of slack.
  • For small projects, managers are often able to memorize and to coordinate all of the various tasks necessary for their completion.
  • For larger projects, however, with numerous activities occurring simultaneously, remembering and coordinating these activities can prove much more difficult. CPM and related tools allow managers to determine which particular tasks most affect the total time of the project and enable managers to better schedule each task so that deadlines are met at the least possible cost
Download Solution PDFShare on Whatsapp

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (23)

Daily Live MasterClasses

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (24)

Practice Question Bank

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (25)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

Critical Path Question 8

Download Solution PDF

Critical activities have

  1. maximum float
  2. minimum float
  3. zero float
  4. negative float

Answer (Detailed Solution Below)

Option 3 : zero float

Critical Path Question 8 Detailed Solution

Download Solution PDF

Explanation:

Critical activity:

Critical activities are those activities whose float is zero and they lie on the critical path.

Float:

Relax or delay provided to any activity is known as float.

Floats are of three types. They are as follows:

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (26)

Total Float (TF):

The maximum delay or relax provided to any activity without affecting the project duration.

TF = Lj – Ei – dij

Free Float (FF):

Relax or delay provided to any activity without affecting the Earliest Start Time (EST) of the successor activity.

FF = Ej – Ei – dij

Independent Float:

Relax or delay provided to any activity without affecting the Earliest Start Time (EST) of successor activity as well as Latest Finish Time (LFT) of the predecessor activity.

IF = Ej – Li - dij

Relation among float TF ≥ FF ≥ IF

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (27)

Critical Path:

  • The longest path in the network diagram is called Critical Path.
  • The length of the Critical Path determines the minimum duration required for the completion of the project.

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (28)

Daily Live MasterClasses

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (29)

Practice Question Bank

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (30)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

Critical Path Question 9

Download Solution PDF

The total float on the critical path in CPM is _________.

  1. negative
  2. positive fraction
  3. positive
  4. zero

Answer (Detailed Solution Below)

Option 4 : zero

Critical Path Question 9 Detailed Solution

Download Solution PDF

Explanation:

Critical Path:

  • Thelongest pathin the network diagram is called theCritical Path.
  • Thelengthof the Critical Path determines theminimum durationrequired for the completion of the project.

Critical activity:

  • Critical activitiesare those activitiesthat lie on critical path.
  • The float of activities that lie on the critical path is zero.

Float:

  • Relax or delay provided to any activity is known as float.

Floats are of three types. They are as follows:

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (31)

Total Float (TF):

The maximum delay or relax provided to any activity without affecting the project duration.

TF = Lj– Ei– dij

Free Float (FF):

Relax or delay provided to any activity without affecting theEarliest Start Time (EST)of the successor activity.

FF = Ej– Ei– dij

Independent Float:

Relax or delay provided to any activity without affecting the Earliest Start Time(EST)of successoractivity as well as Latest Finish Time(LFT)of the predecessoractivity.

IF = Ej– Li- dij

Relation among floatTF ≥ FF ≥ IF

On the Critical path, total, free, and independent float are all equal and zero.

Download Solution PDFShare on Whatsapp

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (32)

Daily Live MasterClasses

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (33)

Practice Question Bank

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (34)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

Critical Path Question 10

Download Solution PDF

The given table lists the project's activities, precedence relationships and duration. Find the critical path of the project.

ActivityPrecedenceDuration (in days)
P-3
Q-4
RP5
SQ5
TR, S7
UR, S5
VT2
WU10
  1. P-R-U-V
  2. P-R-T-U
  3. Q-S-T-U
  4. Q-S-U-W

Answer (Detailed Solution Below)

Option 4 : Q-S-U-W

Critical Path Question 10 Detailed Solution

Download Solution PDF

Explanation:

The project activities, precedence relationships are given below:
[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (35)

From the diagram we can conclude that the critical path isQ-S-U-W.

Download Solution PDFShare on Whatsapp

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (36)

Daily Live MasterClasses

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (37)

Practice Question Bank

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (38)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

Critical Path Question 11

Download Solution PDF

The activities of a project, their duration and the precedence relationships are given in the table. For example, in a precedence relationship “X < Y, Z” means that X is predecessor of activities Y and Z. The time to complete the activities along the critical path is ______ weeks.

Activity

Duration (weeks)

Precedence

Relationship

A

5

A < B, C, D

B

7

B < E, F, G

C

10

C < I

D

6

D < G

E

3

E < H

F

9

F < I

G

7

G < I

H

4

H < I

I

2

----

  1. 17
  2. 21
  3. 23
  4. 25

Answer (Detailed Solution Below)

Option 3 : 23

Critical Path Question 11 Detailed Solution

Download Solution PDF

We are asked to calculate the time along critical path. For complete analysis of critical path we need to do forward pass and backward pass computation. In this question only time is asked, and we know that the time along the critical path is maximum of all the paths in our network so we will directly evaluate the maximum time along any path and mark the answer to save time. Also forward and backward pass computation is necessary if we are asked to find critical path or float related parameters.

In this question “<” & “>” symbols are used to just describe the precedence relationship.

i.e. A < B means A occurs before B.

⇒ On constructing the network diagram with the given precedence relationship.

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (39)

Download Solution PDFShare on Whatsapp

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (40)

Daily Live MasterClasses

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (41)

Practice Question Bank

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (42)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

Critical Path Question 12

Download Solution PDF

A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:

Activity

Immediate predecessor

Duration (days)

A

-

4

B

A

3

C

A

7

D

B

14

E

C

4

F

D, E

9

The minimum project completion time (in days) is ________.

Answer (Detailed Solution Below) 30

Critical Path Question 12 Detailed Solution

Download Solution PDF

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (43)

The minimum project completion time is 30 days.

Download Solution PDFShare on Whatsapp

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (44)

Daily Live MasterClasses

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (45)

Practice Question Bank

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (46)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

Critical Path Question 13

Download Solution PDF

A PERT network has nine activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is

  1. 3
  2. 9
  3. 81
  4. 27

Answer (Detailed Solution Below)

Option 2 : 9

Critical Path Question 13 Detailed Solution

Download Solution PDF

Concept:

In CPM:

The standard deviation of the critical path:

σcp=\(\sqrt {Sum\;of\;variance\;along\;critical\;path} \)

σcp=\(\sqrt {σ _1^2 + σ _2^2 + \ldots + σ _8^2 + σ _9^2} \)

Where,σ12, ....,σ89are the standard deviation of each activity on the critical path

Calculation:

Given:

σ12, ....,σ89= 3

σcp=\(\sqrt {σ _1^2 + σ _2^2 + \ldots + σ _8^2 + σ _9^2} \)

σcp=\(\sqrt {3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2} \)

σcp=\(\sqrt {9 \times 9} \)= 9

∴ the standard deviation of the critical path is9.

Download Solution PDFShare on Whatsapp

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (47)

Daily Live MasterClasses

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (48)

Practice Question Bank

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (49)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

Critical Path Question 14

Download Solution PDF

Activities falling on the critical path have

  1. zero slack
  2. maximum slack
  3. minimum slack
  4. negative slack

Answer (Detailed Solution Below)

Option 1 : zero slack

Critical Path Question 14 Detailed Solution

Download Solution PDF

Explanation:

Critical Path

  • Critical path activities are the project tasks that must start and finish on time according toschedule.
  • A delay in any critical path activity will delay the completion of the scheduled project.

Float or Slack in critical activity

  • Slackor float refers to the amount of timethat various related tasks can be delayed without pushing the schedule.
  • Float is a measure of schedule flexibility.
  • The critical path, by definition, has no slack. But other tasks not on the critical path may have a built-in float.
  • If the Start date and Finishdate for an activity are the same as the schedule, the activity is said to have zero floats.
  • Activities that have zero floats must start on time to prevent the schedule from slipping.
  • Critical activities can also have a negative float.
  • Negative float occurs when an activityfinishes beforethe scheduled date.

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (50)Additional Information

Critical Path Method (CPM):

It is commonly used for those projects which are repetitive in nature and where one has prior experience of handling similar projects. Its is a deterministic model and places emphasis on time and cost for activities of a project.

  • A project can be defined as a set of large numbers of activities or jobs that are performed in a certain sequence determined.
  • A network is a graphical representation of a project, depicting the float as well as the sequence of well-defined activities and events.
  • An activity is any portion of a project which consumes time or resources and has a definable beginning and end.
  • Event is the beginning and ending point of activity or group of activities.

B-D-E-H is the critical path inthe diagram below.

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (51)

Download Solution PDFShare on Whatsapp

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (52)

Daily Live MasterClasses

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (53)

Practice Question Bank

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (54)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

Critical Path Question 15

Download Solution PDF

A project consists of six activities. The immediate predecessor of each activity and the estimated duration is also provided in the table below:

Activity

Immediate predecessor

Estimated duration (weeks)

P

-

5

Q

-

1

R

Q

2

S

P, R

4

T

P

6

U

S, T

3

If all activities other than S take the estimated amount of time, the maximum duration (in weeks) of the activity S without delaying the completion of the project is __________.

Answer (Detailed Solution Below) 6

Critical Path Question 15 Detailed Solution

Download Solution PDF

Concept:

Draw project network and find critical path of network.

Calculation:

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (55)

Various paths in this network are,

1 – 2 – 5 – 6 → 14 weeks

1 – 2 – 4 – 5 – 6 → 12 weeks

1 – 3 – 4 – 5 – 6 → 10 weeks

Hence, critical path is 1 – 2 – 5 – 6 with duration of 14 weeks.

Now, duration of activity S can be increased by 2 weeks atmost.

So, maximum duration of activity S without delaying completion of project is 6 weeks.

Download Solution PDFShare on Whatsapp

India’s #1 Learning Platform

Start Complete Exam Preparation

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (56)

Daily Live MasterClasses

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (57)

Practice Question Bank

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (58)

Mock Tests & Quizzes

Get Started for Free

Download App

Trusted by 5.4 Crore+ Students

Exam Preparation
Simplified

Learn, practice, analyse and improve

Get Started for FreeDownload App

Trusted by 5.4 Crore+ Students


Related MCQ

Basic Concept in Network MCQExpected Time and Standard Deviation MCQTime Estimation Associated with PERT MCQComparison Between PERT and CPM MCQCrashing MCQProbability of Completion of Project Within a Scheduled Time MCQSlack and Float MCQ

[Solved] Critical Path MCQ [Free PDF] - Objective Question Answer for Critical Path Quiz - Download Now! (2024)
Top Articles
Latest Posts
Article information

Author: Margart Wisoky

Last Updated:

Views: 5968

Rating: 4.8 / 5 (78 voted)

Reviews: 93% of readers found this page helpful

Author information

Name: Margart Wisoky

Birthday: 1993-05-13

Address: 2113 Abernathy Knoll, New Tamerafurt, CT 66893-2169

Phone: +25815234346805

Job: Central Developer

Hobby: Machining, Pottery, Rafting, Cosplaying, Jogging, Taekwondo, Scouting

Introduction: My name is Margart Wisoky, I am a gorgeous, shiny, successful, beautiful, adventurous, excited, pleasant person who loves writing and wants to share my knowledge and understanding with you.